Milestone

Target Timeframe

Summation of Activities

Develop test strategy / plan

01/15/2008 - 02/05/2008
~ 15 business days

  • Analyze existing design documents, notes, and other available materials
  • Develop test plan document

Review test plan

02/05/2008 - 02/11/2008
~ 4 business days 

  • Review, clarify, correct, and update the test plan
  • Client approval of test plan

Perform test analysis

//2008 - //2008
~ 4 business days

  • Develop test case design document

Review test case design

//2008 - //2008
~ 4 business days

  • Review, clarify, correct, and update the test case design

Build functional test cases / scenarios

//2008 - //2008
 ~ 6 business days

  • Combine test objectives into test cases
  • Document data, procedures, and results
  • Prioritize test cases
  • Determine which test cases will be executed in different browser/OS configurations

Setup test environment

//2008 - //2008
~ 5 business days

  • Setup web server and database server
  • Load application under test
  • Setup logins and authorizations

Setup test data

//2008 - //2008
~ 2 business days

  • Review & analyze test cases to target data to load in test environment
  • Load initial test data set

Execute functional & exploratory tests

//2008 - //2008
~6 business ~ 6 business days 

  • Execute documented test cases, as well as exploratory tests
  • Communicate with the development team when issues are found
  • Maintain a test run log
  • Track test metrics

Investigate / correct defects

//2008 - //2008
~1 business ~ 1 business day

  • Investigate and validate that a defect has been found
  • Log defects in Jira
  • Work with the development team, as necessary, to identify the cause of the defect
  • Accept and retest defect corrections from the development team

Execute regression tests

//2008 - //2008
~ 6 business days

  • Execute a prioritized subset of test cases as regression of the system once all functional and exploratory testing is complete
  • Validate that no new errors have been introduced as a result of correcting known defects or configuration management / version control issues
  • Investigate and validate that a defect has been found
  • Log defects in Jira
  • Work with the development team, as necessary, to identify the cause of the defect
  • Accept and retest defect corrections from the development team

Execute UAT

//2008 - //2008
~ 10 business days

  • Work with the user community to identify and manage the execution of user acceptance tests
  • Communicate with the development team when issues are found
  • Investigate and validate that a defect has been found
  • Log defects in Jira
  • Work with the development team, as necessary, to identify the cause of the defect
  • Accept and retest defect corrections from the development team

Create test summary

//2008 - //2008
2 business days

  • Create and deliver a test summary report to include:
    • Summation of planned/actual test activities
    • Deviation from planned activities
    • Summary of defects (open defects)
    • Summary of test metrics

Total:

65 business days