ENG File:  P2.eng

Discussion

Timeline

 

Liner Splice Failure

 

...

Observations

•Erosive burning spike was observed in thrust curve, then progresses with normal BATES thrust profile until nozzle failed
•Nozzle cracked at phenolic interface
•Casting tube was likely ejected at +3 seconds around the same time the nozzle cracked, corresponding to the burnout of the aft grain
•Liner surrounding aft grain was ejected at +6 seconds
•Leak path at nozzle crack led to significant loss of pressure and thrust

What caused this?

•Increased Al combustion in high L/D motor raised temperature and interacted with other compounds to enter an uncharacterized combustion regime
•Nonlinearity in burn rate law (r = aP^n) unrelated to Al combustion
•Burning on outside of grains (inside of casting tubes)

Reconstruction of Events

•T-0: The igniter actually works and motor ignites
•T+.5: Erosive burning spike settles down, but motor is now burning at a much higher pressure than expected due to higher Al combustion effect on burn rate law
•T+.5 - 2.9: Thrust curve follows typical BATES profile
•T+2.9: Aft grain burns out, casting tube is ejected
•T+2.9: Interaction with casting tube event along with elevated thermal and mechanical stresses causes nozzle failure
•T+2.9-6.2: Motor continues to burn at lower pressure/thrust due to fewer grains, leakage at nozzle break
•T+6.2: Second grain from aft end burns out, unprotected liner at aft end is ejected due to high velocity gas passing over it
•T+7.8: Motor shuts down

Where do we go now?

•Option 1: Build the same motor again for SAC and reconsider the vehicle’s structure to handle higher loads
•Option 2: Redesign the motor for combustion in the “aggressive” regime, static test it, and then rebuild it for SAC
•Option 3: Redesign the motor for the “aggressive” regime, but don’t static test it before SAC
•Option 4: Descope to 4G motor

How much additional money would the team need to spend to complete each option?

•Option 1: $690 (not including structural redesign)
•Option 2: $1,137
•Option 3: $690
•Option 4: $0