Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Corrected links that should have been relative instead of absolute.

...

The following documents were used as sources of information for this test plan:

2.0 Introduction

2.1 Purpose

...

  • CAMS Use Cases (IdPe)
    • Self-initiated account creation
      • sending activation code via e-mail
      • password strength validation.
    • Self service password reset
    • User may set or modify full name information
    • Users that specify an MIT email address will have their MIT ID number automatically associated with the CAMS account
    • Self service password reset
    • User may register an OpenID accountUser may set or modify full name information
    • User may associate MIT ID number with account
    • Accounts manager password reset
    • Accounts manager may associate MIT ID number with account
    • User may associate alternate security IDs with the account
    • User may associate other email addresses with their account
    • Administrators may set the status of alt_security_id types
    • OverView of Account Admin
    • Account Deactivation
  • IdPi Use Cases
    • TBD
    • Username/password
      • Cookies enabled/disabled
      • Javascript enabled/disabled
    • Kerberos
      • Cookies enabled/disabled
      • Javascript enabled/disabled
      • With and without valid tickets
    • X.509 User Certificates
      • Cookies enabled/disabled
      • Javascript enabled/disabled
      • with and without valid certificate installed
    • Preference for authentication method via cookie
    • Open issue - variety of browsers supported (question mostly about mobile support)

** Currently there are 17 ** Currently there are 17 total use cases identified for CAMS and none for the IdPi. This document assumes an estimated 50 total use cases for planning purposes.

...

The following modules and types of tests are considered to be outside the scope of immediate test effort.  As functionality is added, test cases for this test effort and will not be tested by Questcon. Testing may be performed by internal MIT personnel:functionality will need to be developed.  Immediate test planning focus should be on CAMS versions 0.5 and 0.6, continuing to later versions as time progresses.

  • CAMS Use Cases (IdPe)
    • Sponsored account creation
    • Sponsor may review a list of accounts that they have sponsored
  • IdPi Use Cases
    • TBD

...

Type of Testing

Included
Y/N

Comments

Team Responsible

Automation

N

MIT personnel will utilize jMeter to automate portions of the backend testing; no test automation tools will be used for the UI testing (use of Flash prevents this ??).

N/A

Conversion

N

There is no pre-existing system; therefore no data conversion is necessary.

N/A

Exploratory

N Y

Some level of exploratory testing will be conducted based on heuristics related to typical rich-content internet applications.

Questcon N/A

Functional

Y

Functional testing will be performed based on test cases derived on the documented use cases and front-end functional design.

Questcon

Installation / Upgrade

N

Because this is a web application no installation testing is necessary.

N/A

Integration

N Y

Some integration testing will naturally occur as the front-end of the Touchstone application interfaces with and utilizes the back-end APIs.

Questcon N/A

Parallel

N

There is no existing system that Touchstone is replacing.

N/A

Performance

N

Performance testing is coved by a separate Test Plan.

N/A

Regression

Y

Questcon expects to run at least a minimum regression test set prior to release to production.

Questcon

Security

Y

Backend security testing will be done by MIT. Questcon will execute basic security/login testing on the front-end

MIT - Tester (backend)
Questcon (front-end)

UAT

Y

The user community will be tasked with performing ad-hoc user acceptance testing, domain specific metadata testing (metadata titles, tag lists, etc.), as well as previously designated documented functional test cases for multiple browser/OS configurations (primarily Safari or Firefox/Mac configurations).

MIT - User Community

Unit

Y

Questcon expects the MIT developers to perform unit testing prior to releasing code to the test environment.

MIT - Developers

...

3.3.1 IdPe Server Configuration

Hardware

O/S

Other TBD

Virtual Machine

RHEL3 TBD

  • Apache
???
  • Tomcat ???
  • Openssl ???
  • Mod-
    • 2.0
    • Tomcat 5.5.25
    • Openssl 0.9.7+
    • mod_jk ???
    • Jdk
    ???
    • 1.5.x
    • reCAPTCHA
    • MySQL 5.x
    • Shibboleth IdP 1.3.3
    • Spring/SASH stack 2.0.7
    ???

    This information is an assumption and will be updated when MIT specifies what their production server configuration will be.

    3.3.2 IdPi Server Configuration

    Hardware

    O/S

    Other

    Dell TBD
    TBD

    RHEL3

    • Apache
    ???
  • Tomcat ???
  • Openssl ???
  • Mod-
    • 2.0
    • Tomcat 5.5.25
    • Openssl 0.9.7+
    • mod_jk ???
    • Jdk
    ????
    • 1.5.x
    • Shibboleth IdP 1.3.2
    • Stanford WebAuth 3.5.4 (with local mods)
    • Perl 5.8.x
    • mod_auth_kerb 5.3? (with local mod)
    ??

    This information is an assumption and will be updated when MIT specifies what their production server configuration will be.

    ...

    Hardware

    O/S

    Other

    PC

    Windows XP Professional SP 2

    • Mozilla Firefox v2+
    • Microsoft IE v7

    Macintosh PowerPC

    Mac OS X

    • Firefox v2+
    • IE v7
    • Safari v2+

    Mobile Platforms

    TBD

    TBD

    This information is an assumption and will be updated when MIT specifies what their desired client configuration will be for the purposes of this testing phase.

    ...

    Key Deliverables

    Description

    Expected Delivery Date

    Resource

    Test Plan

    This document.

    After all needed data is delivered (first half March 08)

    Questcon

    Test Case Designs

    List of objectives and priorities of the tests.

    4 business days after test plan is approved and necessary information and environmental needs met.
    This is based off an estimated 250 test cases.

    Questcon or MIT designated resource

    Test Cases

    Steps and expected results.

    6 business days after test case design completeion.
    This is based off an estimated 250 test cases.

    Questcon or MIT designated resource

    Status Reports

    Accomplishments, issues and plans.

    Weekly

    Questcon or MIT designated resource

    Test Logs

    Test execution data that indicates test run status, number of test runs and test metrics summaries.

    Ongoing during test execution

    Questcon or MIT designated resource

    Defect Reports

    Entered in Jira as they are discovered.

    Ongoing during test execution

    Questcon or MIT designated resource

    Test Summary Report

    Details the results of the testing effort.

    2 business days after test execution is completed.

    Questcon or MIT designated resource

    ...

    The planned test schedule of the Touchstone project does not has an anticipated start date or completion date set yet. All dates are subject to several assumptions, some of which have been identified in 2.3 Risks & Contingencies.

    Information below is null and void, working with new Questcon contractor to revise and update the schedule during the first week of March 08. 

    Milestone

    Target Timeframe

    Summation of Activities

    Develop test strategy / plan

    01/15/2008 - 02/05/2008
    ~ 15 business days

    • Analyze existing design documents, notes, and other available materials
    • Develop test plan document

    Review test plan

    02/05/2008 - 02/11/2008
    ??~ 4 business days ??

    • Review, clarify, correct, and update the test plan
    • Client approval of test plan

    Perform test analysis

    //2008 - //2008
    ~ 4 business days

    • Develop test case design document

    Review test case design

    //2008 - //2008
    ~ 4 business days

    • Review, clarify, correct, and update the test case design

    Build functional test cases / scenarios

    //2008 - //2008
    ~ 6 business days

    • Combine test objectives into test cases
    • Document data, procedures, and results
    • Prioritize test cases
    • Determine which test cases will be executed in different browser/OS configurations

    Setup test environment

    //2008 - //2008
    ~ 5 business days

    • Setup web server and database server
    • Load application under test
    • Setup logins and authorizations

    Setup test data

    //2008 - //2008
    ~ 2 business days

    • Review & analyze test cases to target data to load in test environment
    • Load initial test data set

    Execute functional & exploratory tests

    //2008 - //2008
    _~ 6 business days _

    • Execute documented test cases, as well as exploratory tests
    • Communicate with the development team when issues are found
    • Maintain a test run log
    • Track test metrics

    Investigate / correct defects

    //2008 - //2008
    ~ 1 business day

    • Investigate and validate that a defect has been found
    • Log defects in Jira
    • Work with the development team, as necessary, to identify the cause of the defect
    • Accept and retest defect corrections from the development team

    Execute regression tests

    //2008 - //2008
    ~ 6 business days

    • Execute a prioritized subset of test cases as regression of the system once all functional and exploratory testing is complete
    • Validate that no new errors have been introduced as a result of correcting known defects or configuration management / version control issues
    • Investigate and validate that a defect has been found
    • Log defects in Jira
    • Work with the development team, as necessary, to identify the cause of the defect
    • Accept and retest defect corrections from the development team

    Execute UAT

    //2008 - //2008
    ~ 10 business days

    • Work with the user community to identify and manage the execution of user acceptance tests
    • Communicate with the development team when issues are found
    • Investigate and validate that a defect has been found
    • Log defects in Jira
    • Work with the development team, as necessary, to identify the cause of the defect
    • Accept and retest defect corrections from the development team

    Create test summary

    //2008 - //2008
    2 business days

    • Create and deliver a test summary report to include:
      • Summation of planned/actual test activities
      • Deviation from planned activities
      • Summary of defects (open defects)
      • Summary of test metrics

    Total:

    65 business days

    _ ** This estimate could change depending on the actual number of test cases, complexity of test cases, or items we are not aware of at this time._