Manufacturing Fin Can

 

1. Prepare Overwrap Materials

High temp vacuum bag

20" x 22"

Low temp vacuum bag

20" x 22"

Breather cloth

14" x 20"

High temp peel ply

14" x 20"

High temp release film

14" x 20"

Butcher paper

14" x 30"

Carbon fiber

14" x 30"


2. Layup Phenolic Tube

  • Systems 3000 epoxy applied to carbon fiber (3)

  • 2-3 team members

  • 3-4 hours

  • Consistent set-up & execution needed




3. Phenolic Tube Cure

  • Cure at room temperature in low-temp vacuum bag for 24-36 hours

  • Oven cure for an additional 12 hours in high-temp vacuum bag

 

4. Attach Fins to Fin Can

 

5. Apply Root Fillet to Fins

 

  • ¾” radius Systems 3000 epoxy with 9% cabosil

  • Each pair of fillets require 18-24 hours to cure

  • Each pair of trailing edges require 18-24 hours to cure

 

6. Prepare Tip-to-Tip Materials

High temp vacuum bag (4)

20" x 22"

Low temp vacuum bag (4)

20" x 22"

Breather cloth (4)

14" x 20"

High temp peel ply (4)

14" x 20"

High temp release film (4)

14" x 20"

Butcher paper (32)

12" x 18"

Carbon fiber (32)

12" x 18"

12" x 22"

14" x 22"


7. Layup Fin Can Tip-to-Tip

 

  • Systems 3000 epoxy applied to carbon fiber (4x8)

  • 4-5 team members

  • 3-4 hours

  • Consistent set-up & execution needed


8. Mitigating Wrinkles

  • Do not exceed pot life of the epoxy → can’t be pulled out later

  • Ensure that the carbon fiber doesn’t bunch up / shift during layup

  • Use extra breather to prevent the vacuum connector from denting carbon fiber

  • Double check vacuum is connected correctly

  • Minimize wrinkles in all layers: release film, peel ply, etc.

  • Don’t use the foam technique near the fillets unless we know it’s gonna work

  • Make sure there is not a lot of excess carbon fiber near the fillet (needs to fit the profile pretty closely)



9. Fin Can Cure
  • Cure at room temperature in low-temp vacuum bag for 24-36 hours

  • Oven cure for an additional 12 hours in high-temp vacuum bag

Manufacturing Testing Jigs




Tentative Schedule


Week 1

Assemble new manufacturing jigs.

Establish fin can testing jigs.

Prepare overwrap kit for phenolic tube #2.

Week 2

Cut G10 fins on waterjet. 

Apply root bond and begin fillets for fin can #1.

Prepare tip-to-tip kit for fin can #1.

Week 3

Overwrap and cure phenolic tube #2.

Finish applying fillets to fin can #1.

Prepare tip-to-tip kit for fin can #2.

Week 4

Apply tip-to-tip and cure fin can #1.

Apply root bond and begin fillets for fin can #2.

Prepare overwrap kit for phenolic tube #3.

Week 5

Overwrap and cure phenolic tube #3.

Finish applying fillets to fin can #2.

Prepare tip-to-tip kit for fin can #3.

Week 6

Apply tip-to-tip and cure fin can #2.

Apply root bond and begin fillets for fin can #3.

Test fin can #1.

Week 7

Finish applying fillets to fin can #3.

Test fin can #2.

Week 8

Apply tip-to-tip and cure fin can #3.

Test fin can #3.